Sound Isolation for Single Room in Basement
Recent Status Update -
The finer things like trim and acoustics are underway.
Lighting has been completely wired and power to the room is all set.
The room is fully functional for isolation and we've been able to have weekly rehearsals during nap times for the family. - This was my stated goal, so I am happy.
Upcoming things are the moulding around the ceiling, cutting holes for the other two windows, and hangers for instruments and cables.
External image, not preserved — original: http://www.johnlsayers.com/phpBB2/files/rookieroom_830.jpg
End Recent Status Update
Reference Section
Drum Riser - Using rockwool directly on the floor with mdf or other framed surface as mass on top to deal with frequency transmission. Pretty cool and addresses the fundimental problem. Anyone new to the concept can easily deduce WHY this is a good method. There are ancilary points bantered about, but the concept is the same.
Nails through the Subfloor into the basement? - this was my query to the group which was answered and I followed through on the advice in this thread.
Insulation contacting the surface it's installed against - this was a simple question I had in mind when starting this build. It was helpful. Just info about how to deal with laying or applying the insulation. Good info...
Insulation info that was helpful
Door Seal Good suggestion there.
Knightfly - Good advice on how to transform a normal door frame into a better form of isolation
A good way to frame a door - useful.
Other door research I found useful.
Building Panels -noted this as good somewhere in this thread.
Fabric for covering room treatment
Johnsmainville - Brad; "I paid $80.13 for 9 panels (72 sq. Ft.) " on 2/10/2008.
Vertustudio - Want to see a project where the builder has some skills in detail work? Check out the clean work on the doors. Hats off to you sir! Great workmanship.
Vertustudio Doing a fantastic job of room treatment. Check out his upper corner trap constructed as a triangle frame.
Jester Used the same electrical boxes and putty packs as I did.
Now for the Build Intro
I’m in the beginning of construction for a 1 room jam room in our basement of a modified Cape in New Hampshire. It is not a huge space and doesn’t need to be. My basic goal in this is to have a place I can turn up to modest levels and not interfere with others enjoying what they are doing (talking on the phone, sleep, touchy part of a chick flick…).
I’ve had Rod’s book for the better part of a year now and most of my reading has been to do with the construction techniques in framing, drywall and insulation as well as door framing. Honestly, it’s that way because I’ve done carpentry and woodworking for years – easiest to wrap my head around. I’ve done less reading of electrical in areas of my concern for this room.
I’ll do my best with photographic detail. I am not set up with a competent architect program to draw wall and flooring detail at the time, but the start of construction after much reading on this forum has me starting my thread anyway. I’ve poked around to see a few named on this forum, but wonder if someone might suggest one over another and the reasons why.
Type of music we play is rock/blues/pop. Mostly, myself and two of my brothers are the ones playing music. I make cabinets and chassis for amp heads so I always have an ample amount of speakers and power behind them. We’re not terribly loud, but with no insulation to speak of right now I feel guilty playing while my wife is with our young daughter upstairs.
The nearest neighbors are hundreds of feet away so noise really isn’t that much of an issue. My concern is for the people within the house.
Basement Construction Details.
Location Southern NH. House constructed in 1976.
Code – I’ve only approached our town with putting layers of drywall within the joists. Stating that I am doing only this and insulation underneath that as my isolation to get the ok with the passive load. I did this because at the time I was introduced to the inspector it was the only thing I knew I was planning on doing. I wasn’t sure about the area of the basement this was going to be constructed within and there were plumbing boundaries in both areas, so with the measurement of each section we had a good conversation. I’m ok for several layers of drywall and more because the span is so short (9 & 10 feet) in this area of the basement. .
Floor Joist – 2x10
- - Span – 10’ & 11’ on either side of center support beam.
- Support Beam – Triple 2x10 w/columns & chimney foundation/footing in middle of house.
- Span: Beam spans foundation wall to center chimney footing with 2 column supports.
- Support Column Positioning: The room span is 14 feet with the middle column supporting 6’ in.
- - Voids - The mdf looks to be fitted properly from what I see in the two carpet sections of the house I replaced not too long ago. I’m not taking up the hardwood flooring to check, but this house does appear to be put together properly. I do not notice any issues with the plywood attached to the floor joists.
- - Bathroom Plumbing – The water supply and the drain pipes (pvc) which dip down for their trap section. Some of this will be rerouted to the foundation wall to enter the main outside of the room.
- Copper Piping - Forced Hotwater Heat and Water supply for bath. ½ and ¾ tubes. I would love to move these to run in the same area as the shower/toilet drain pipes, but I’m not sure the expense/benefit will be worth it.
- - Question: With having one layer of ½ drywall in place, I’m left thinking I should put the next layer as 5/8 drywall as it would handle a lower level of frequencies in isolation. Which would be better; 2 more layers of ½ drywall or one more layer of 5/8?
- Resource I’ve Found BACKER ROD: My brother works with commercial glass. He installs glass in anything from see through flooring for high end condos in beacon hill to plate glass for office buildings. I had purchcased the first round of this stuff from Hell Depot and was bitching about it being too small of an amount and that I was looking for spools of it. So: I may have a resource for anyone needing some in the area. Please respond to this thread or PM my username to get some from me.
- - Is there anyone with experience in framing walls on or near a basement drainage system?
- Drain for Tub having a hole. Can someone recommend an example for constructing an access panel that still provides isolation?
- Two sides of the beam having differently framed and attached ceiling construction. Is this more effort than needed? Advice?
- Double wall assembly spacing: as noted, the non foundation wall will be a double wall assembly and will contain the sole door to the room.
- Windows: what to do and how to construct around these.
- Next layer of Drywall in between studs? 5/8 or 2 layers of ½?
- Walls as they are attached to the slab - Should I use pressure treated wood on the bottom of my frames? Flood is not a concern, but moisture is. Anyone have experience with this or is it not much of a concern?