Morning fellow builders – I hope you’re all OK and looking forward to the festive season and time spent with your loved ones. :D :D
So, what have I been up to since my last post? Well, mainly ploughing through the ‘mash’ of paid work I mentioned, coping with one frustration after another, and facing the fact that it’s just not possible to be in two places at once! :evil:
As the end of the outer-leaf looked imminent, we ran out of stickpins and rockwool. I ordered some more which arrived promptly last week except that the stickpins turned out to be part of a bad batch and so basically don’t stick ! Great……………not. :evil: :evil:
One of the three kitchen appliances that we didn’t replace was the washing machine. Chris made a predictably ‘top job’ of fitting it and then two days later, guess what? ………………………yup! It packed up. :evil: :evil: :evil:
So, we decided to buy a new one since the cost of repair was uneconomical, but whilst it was the same width, it was slightly deeper front to back, and so I had to get Graham back to recess his mains sockets into the wall. OK, no big deal I know, but now Chris has to figure out how to get a door on the front that will open out and swing to the left so that we can still open the soap dish! :evil: :evil: :evil: :evil:
One good thing that came out of this, is that it prompted me to finally ‘tee’ off the hot and cold feeds and runs the water supplies into the studio as you’ll see, and I’ve got some good progress to report on the air-con side. :wink:
My main frustration though is that due to our three month delay in starting, the crap weather, the angry neighbours, and my busiest time of year, we are still way behind and realistically, Studio 4 will not be ready by mid January. I now have no alternative but to get some help from a pro studio builder, and Chris. :cry: :cry:
I know that all of us have had frustrating times, but Man doesn’t it really grind you down? :roll:
Anyway, here’s where we are, and a brief plan of what’s next. Enjoy!
Superslab under front window.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/148-4893_IMG.jpg
The nerdy accuracy of these edge cuts enabled us to get a nice fitting butt joint to the vertical from the pitched roof section, if you get my meaning. :?
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/148-4894_IMG.jpg
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/148-4895_IMG.jpg
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/148-4896_IMG.jpg
Some of the stickpins that did stick!
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/148-4899_IMG.jpg
Side view of Studio entrance. :shock: :shock:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/149-4901_IMG.jpg
You never know what surprises you’re gonna’ find in the back of your car, but in this case it was six custom made silencers. 4 at 1.5m x 200mm x 200mm, 2 at 1m x 150mm x 150mm and a box of 20mm flanges! Result. :wink: :wink:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/149-4902_IMG.jpg
They’ll obviously look better when they’re installed, but I’m real pleased they’re at last now in the studio and not in my dreams.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/149-4903_IMG.jpg
They’re naturally directional with solid steel panels at the inlet end and perforated steel at the other. :?
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4905_IMG.jpg
It was then time to get on with the one job I was really avoiding – the ‘tee-off’ The main reason for being so concerned about this was not only that the wall in question was now 13 ½ “ thick, but also that on the other side I now had to get through my plasterboard - MDF - plasterboard sandwich!!
Here’s the step by step:
Mark pipes, and turn off the water with the isolating valves you’ve already installed.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4906_IMG.jpg
Purchase evil drill bit! (SDS regular chuck adaptor).
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4907_IMG.jpg
Cut pipework on the correct side of the valves and drill away, and then go real slow when you start to feel that you’re through the first layer of brick, crossed the cavity, gone through the second layer of brick, and reached the all important mark you pre-measured on the drill bit that tells you – you're now into plasterboard, Lou. :wink:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4908_IMG.jpg
Panic like hell on your journey to investigate, and then breath a sigh of relief as you’re greeted with exactly the result you wanted.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4909_IMG.jpg
This is of course only the first of two pilot holes, making it possible to get the ‘big bugger’ back through from the studio side! (Outside tap for size comparison).
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4912_IMG.jpg
I had to do it this way around since the studio floor is a good two feet below the kitchen floor. Make necessary connections on the kitchen side.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4910_IMG.jpg
Then go back in the studio to make sure the two bits of pipe you’ve just plumbed in are long enough! :roll:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4913_IMG.jpg
Make all necessary connections on the studio side so that the water can be turned on again without flooding the studio! Take ‘arty’ shot to present to forum.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4915_IMG.jpg
The top valves will feed the studio toilet hand basin, and the bottom ones will connect down to the two pipes that are already laid in the screed to feed the studio kitchen. Voilâ!
Then realising again the ludicrous expense of having crap removed, I decided to organise grab no 9! (£305.00 inc vat) and get the front of the house looking a little tidier! :evil:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4917_IMG.jpg
Yesterday (Sun) my air-con chap phoned and asked if he could drop some of my gear over to clear some space, “of course“ I said, Now this is what I call a van.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4920_IMG.jpg
The exterior condensers – yes guys, I’ve ordered all my air-con! :shock:
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4921_IMG.jpg
And here’s the first lot of ducting to go with the silencers.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4923_IMG.jpg
The internal units are currently being modified and arrive later in the week along with the rest of the ducting.
Now I know you all want far more info on this than I’m currently providing, but I truly don’t know what I’ve ordered! :oops: :oops:
I’m relying on the people I trust who recommended this Guy, his reputation, past clients and the general impression I get etc. We’ve had three lengthly meetings, he’s well aware of my requirements, gear going in, lighting, no of people, room dimensions etc, he’s quoted a very sensible price, and he’s asked for 50% up front, and the balance to be paid when the system is fully installed and running as intended – SILENT! – EFFICIENT! And generally able to do what I want it to in a fully working situation.
Naturally I’ll be documenting everything and posting the progress.
Most of our weekend was spent getting our ‘field’ kichen out of the sitting room and into the chill-out area, so that we can at last get everything put away and our house properly cleaned up in time for Christmas.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4929_IMG.jpg
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4926_IMG.jpg
Arty shot to finish of chill-out area from kitchen opening.
External image, not preserved — original: http://i195.photobucket.com/albums/z194/m2uso/album%20name/149-4930_IMG.jpg
Also since my last post, I’ve got 14 tracks out for a Christmas show and done half of last years accounts. My accountant is screaming for them before the holidays, and as any UK’er will tell you, the end of Jan deadline for tax returns is a deadline you really don’t want to be missing!
The air-con is being installed between Christmas and New Year, although the rest of the gear is arriving soon and maybe even a start on that is planned for later in the week!
That’s it for the mo chaps, more to follow as it happens,
Stay tuned,
Regards as always good people,
Lou. 8)