CR Treatment and Tuning---The home stretch!!

Started by Stadank0 on 3 January 2018. 649 replies, 2018–2021. In the Library under Acoustic treatment. Key posts in this thread.

Originally posted at johnlsayers.com, topic 21368.

I'm not worried about getting all the way up to 800 ms. I'm sure I could do great things with 600 ms..Wouldn't mind staying a little on the tighter side. Good to know either way....back to the desk.
That's why the second work station has been so useful up till now...there is enough clarity at that those decay times. Hoping we can find a way to make that second work station still usable even if we up the decay! Still need it for electronic music and playing virtual instruments. Probably gonna be tough to do....
That's why the second work station has been so useful up till now...there is enough clarity at that those decay times. Hoping we can find a way to make that second work station still usable even if we up the decay! Still need it for electronic music and playing virtual instruments. Probably gonna be tough to do....
How about if we go for variable acoustic devices? That way you can "eat your cake and have it too".... Change the response time as needed for tracking, or mixing, or whatever.... Interested? - Stuart -
Oh I'm interested!!! Questions is, how many lifetimes will it take??? :P :P :lol: :lol: :lol: :mrgreen: :mrgreen: :mrgreen:
That depends: how many lives do you have? :) :shot: - Stuart -
Well, this one's already on loan...I'll have to depend on your good will... :cop:
Emailed you a question about the desk.
Milling commences.....Always goes slower than I hope for...Should have the desk done inside of 2 weeks all the same.
Image not preserved: 20181114_130435.jpg
Image not preserved: 20181114_130446.jpg
Milling commences.....Always goes slower than I hope for...Should have the desk done inside of 2 weeks all the same.
:thu: Keep the photos coming! I love watching how your place is coming together.... And so do lots of other people, who seem to be quietly following your thread. There's over 26,000 views, so far... Also, I'm starting to work on a plan for improving the Live Room... - Stuart -
Could only get a few hours in today, but at least I got something done. Stuart, Sketchup is running really slow and hanging up a lot these days. Are you having any issues with the model on your end?
Image not preserved: 20181116_175552.jpg
Sketchup is running really slow and hanging up a lot these days. Are you having any issues with the model on your end?
The model is getting to be pretty big now, with all the details in there. It's around 85 megabytes. SketchUp start bogging down with files that big, on systems that don't have a lot of CPU power, RAM, or graphics power. I had to buy a maxed-out system for the same reason, a couple of years ago (8 CPU cores, 16 GB RAM, SSD, Nvidia graphics, etc.), just so that I can deal with large models. I've been complaining to Trimble for years about the slowness of their product on large models, as have many, many other users, but they don't seem to care. With each new release, they insist on adding even more "features" that aren't much use to anybody, rather than fixing all the bugs in the existing code and adding the features that users really want. Go figure! Not a very user-friendly company. And they charge a small fortune for the "Pro" version, which I have to buy so I can do commercial work with it.... Excuse the rant! Anyway, what you could do, is export just the desk to another file, and work on it there. Double-click down through the layers, until you have just the desk highlighted, then right click and select "Save As" from the menu. Give it a different name, close the full model and open the desk-only model. It will go much faster. - Stuart -
:thu: I have an i9 8 core cpu with 64 gigs of RAM(for music sample libraries),ssd, a good nvidia card and its still sucking, so I don't think its the hardware on my end either.
Got some much needed rain coming our way...Will probably be slowed down a day or two during the stain and clear coat process. The hours do rack up! No pun intended..... :mrgreen: Stuart, can I get rid of a bunch of Denim insulation that I have? I doubt you'll use it in the LR. I'm guessing 703 all the way!
Image not preserved: 20181117_153510.jpg
Image not preserved: 20181118_160441.jpg
Image not preserved: 20181118_174453.jpg
More progress...You can see the smoke form the fires in the background. Its getting a bit better now.
Image not preserved: 20181119_170817.jpg
Looking pretty good, Frank! And going pretty fast, as well! Wow. I didn't realize the fire was that closet to you: and I'm REALLY glad that the fire didn't get to your place! That would have been major tragic. - Stuart -
The major fires aren't close, but there are several fires that have popped up around me in the meantime. Fortunately, our firefighters are amazing and have put them all out quickly. If there was any serious wind as well, then things would probably have gone much worse. We got rain coming tomorrow night, so I think we're safe for awhile after that.
Well despite getting a sinus infection from sawdust and smoke and Thanksgiving going on, I managed to get some work done. Still have to do all of the clear coats and got rain tomorrow. I expect to have the desk done no later than next Wednesday. I'd get it done sooner if it wasn't for the clear coats...
Image not preserved: 20181122_181703.jpg
Image not preserved: 20181122_181706.jpg
Happy Thanksgiving! (Belated... but better late than never, I guess). The desk is looking good, too! - Stuart -
In case anybody thought I was slowing down....Should be done by tomorrow night!
Image not preserved: 20181126_133542.jpg
Wow! That's going REALLY fast, Frank! And it looks like the "vented rack blank" idea is working out pretty well, too. - Stuart -
Got some 1/4" air filter foam material coming to glue onto the backs of the vents to keep the dust out....And yes it will breath! :)
Stadank0 wrote:
Got some 1/4" air filter foam material coming to glue onto the backs of the vents to keep the dust out....And yes it will breath! :)
:thu: - Stuart -
Hi Frank ! Wow, that looks really good !! QUESTION: WHERE did you get those steel plates (with the perforated holes) from ? I'm finishing my racks now, but I have no idea where to look for those -- and what they might cost ? Looks like they were pre-made with the holes for the rack screws already drilled out.
Hi, I got the sheet of off of ebay. If you look up perforated sheet metal, you should get results. Pretty sure that's what I did. Mine is aluminum which I recommend for weight and ease of cutting. To be clear, The covers on the back are standard rack vents. I only did the sheet on the desk top. Here is the link to the one I bought: https://www.ebay.com/itm/Perforated-Met ... 2749.l2649 Your desk is insane compared to mine!! :lol: In case your interested in the vented rack blanks, I got them here: https://www.pennelcomonline.com/