Ok, been busy with the LA AMP Show and other fun stuff, but I finally got back to see what was
going on with the demo room.
The electrical is all in, the dual 2x4 stud walls with their dual 5/8" sheetrock on the outside, and
2" gap are all in as well. The 1st layer of 5/8" has gone up on the inside, mudded and taped, it's
now drying. The next layer with the Green Glue goes in on Monday. The doors will go in on
Tuesday (solid core 36" wide, dual doors per opening) and then get thresholds that are fit for them.
Storage unit w/functioning garage door. This room will get one more layer of drywall all
around w/Green Glue on the walls next to the demo room (back and right side in the photo).
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0488.jpg
Office/workroom. This room gets another layer of drywall w/Green Glue on every surface.
I'm going to have a "hatch" made for the window, which will swing away on hinges. It's going
to have a 2x4 frame inside, with dual sheetrock layers front and back. The plan is to make
it a press fit with a thin layer of material to compress (likely industrial carpet), with the
sheetrock overlapping the edges about 1".
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0493.jpg
Demo room, dual 2x4 walls, 4 layers of 5/8" drywall, R13 insulation, 2" air gap between the
walls, plus an 11" air gap between the outer 2x4 wall, stuffed with R30 insulation (12" thick),
and then there's the steel garage door. If this proves to be insufficient, I'm just going to put
plywood on the outside of the garage door. At this point that wall (the weakest link) will be
about 2 feet thick. Crossing my fingers on that one, although the amps will be pointed away
from that wall and towards the back of the structure.
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0494.jpg
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0495.jpg
My contractors seem to have some political statements about the recent legislation
move for marijuana in California. :wink:
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0496.jpg
Up in the top of the garage, I decided to do it all. In the rooms below, there's the two layers of 5/8" for the ceiling
(2nd layer w/GG on Monday), plus R13 insulation, then 3/4" pine tongue in groove on top of the insulation.
Above that is R30 insulation, and then I had 3/4" plywood run from end to end over the entire structure (30x24).
My wife will love the storage. My dog is dying to climb the ladder to go up there and check it out. I had all the
joists reinforced and extra bracing put in specifically for the plywood to attach to. It's pretty tight in there for
walls, and when you thump on the drywall now, it doesn't reflect back a lot of sound.
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0489.jpg
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0490.jpg
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0491.jpg
External image, not preserved — original: http://www.southbayampworks.com/dr/DSCN0492.jpg
More pics next week. I do my 2009 taxes tomorrow so I need to see how much the IRS is leaving me
to finish this project. As you can imagine, it's gone way over the original estimates due to problems
with the structure that needed fixing. Between materials and labor, I'm somewhere around $14K at
this point, with about 2k more in labor, materials, paint, etc.