here's my orginal post when I started this project in April ('06)
http://johnlsayers.com/phpBB2/viewtopic ... highlight=
when I first got the house ( from what is now the control room looking into what is now the live room )

when I first got the house ( from what is now the live room looking into what is now the control room and iso )

designing the mic panel ( sketchup rocks! )

removing the drywall in a way that I could reuse it ( jig saw with a SHORT blade!!)

removed drywall panels

beefing up the outter leaf:
old insulation removed and original drywall glued to siding with silicon caulking ( held it up, but was not rigid, and provided resilience between the two layers of the outter leaf )

control room wall going up, also floor for the iso

3rd layer of drywall attatched to outter leaf ( with silicon caulking in between ) and cleated w/ small pieces of wood ( 12"X.5"X1" appx )

Live floor, 24" centers, fibrex mineral wool, mass loaded vinyl on top for resilience between MDF and floor joists which are on auralex u-boats

framing of iso walls and ceiling going up!

finnished live room! ( more pictures on my other comp of the live room framing, drywall, insulation, RCs )


Iso booth looking into live room