Ceiling and Walls
Posted: Wed Jan 14, 2004 1:40 am
John: Were finally underway. Because of timing of contractors drywall on front wall (right in picture) and ceiling in front of control room may need to be installed before side wall framing (foregorund and rear of photo) for interior sliding doors are intalled. Will this compromise the isolation provided by the resilient channel? At miniumum it seems to me that side top wall plates will need to be screwed through the drywall into the resilient channel (not the joists). Would it be critical to hang only the center part of the ceiling and then put up the framing for the side walls? Does it trouble you that the top plates for the side walls will be installed on the already hung resilient channel?
Geoff
Geoff