i was speaking with a ready mix concrete about ordering concrete for my footings gave all dimensions etc all fine . but needed a pump for the concrete so he was going to call me back with when he could get the pump. i was out but my brother took the call and sorted the date, as i asked him to do. but he told my brother somthing about getting a bag of cement / dusting ?. does any one know why this is? thanks for any help.
concrete
Originally posted at johnlsayers.com, topic 9246.
any ideas people. thanks
Joey,
you should call him back to verify (a single bag sounds a bit low to me -
but he must want you to have the material to make a slurry mix - which is sort of like greasing the hoses before they try to pass the concrete through - it helps to stop the aggregate from getting stuck.........
Rod
cheers rod. called him this morning and it was for priming the pump. ive got a few more bags of cement as well.