The guys installing the drywall used a full schedule of screws on the first layer, even though I told them otherwise.
Do we pull the screws and mud the holes? Or are we better off leaving the screws?
I need to tell them something by tomorrow morning... Any quick advice would be very welcome:)
thanks,
andrew
emergency drywall screw question
Originally posted at johnlsayers.com, topic 4537.
Leave the screws
Rod
Right; in fact, some local codes won't even LET you use half-schedule on ANY layer (Californicate :? )
Thanks guys! that's a bit of a relief...
can't wait for this to be over with... talk about epic!