emergency drywall screw question

Started by aschatzb on 17 October 2005. 3 replies.

Originally posted at johnlsayers.com, topic 4537.

hello, The guys installing the drywall used a full schedule of screws on the first layer, even though I told them otherwise. Do we pull the screws and mud the holes? Or are we better off leaving the screws? I need to tell them something by tomorrow morning... Any quick advice would be very welcome:) thanks, andrew
Right; in fact, some local codes won't even LET you use half-schedule on ANY layer (Californicate :? )
Thanks guys! that's a bit of a relief... can't wait for this to be over with... talk about epic!