Monday April 19th
Guys arrived a bit before 9. José had to deal with his car and would be coming after lunch. Metal shutters were supposed to come at 16 and did not. They removed the framing of the cement above the windows and door today. Looks good. Gil put up two more layers of bricks so we are up to 2.9m now in the front of the building and on one side. This will slope up to 4.5m in the back.
Cement for the back wall has been ordered in for thursday. They are supposed to get the metal shutters tonight at 19 and bring them tonight. Paul will look into the windows tomorrow. Had a talk with Joe and he clarified a few things but Paul still want to talk to him.
Tues April 20th
José did come with two other guys at 19 last night with the panels. They used the crane to unload them. Now for sure they will finish the framing of the back wall today.
Spoke to Joe and we agreed that the inner walls we will have a 5cm gap between the brick wall and the frames wall. The framed wall will be made with metal framing (5cm) with one layer of plasterboard on the brick facing side, filled with rock wool and two layers on the outside. The most outer layer damp resistant. This will make the walls about 13cm thick to give us a bit more room in the live room.
Windows will be normal double pained glass with reflective mirror on film for the exterior for all windows. All the internal windows will be normal double pained glass except the live and control room, which will be laminated inside to provide less sound reflection.
Weds April 21st
It was ok weather in the morning but the rain really picked up in the afternoon and they had to quit a bit early but they are ready for pouring the concrete tomorrow for the back wall. Just one small section they have to foam up and it is ready to go. Exciting. Only took a couple of pictures today.
Gear for the studio arrived today. Now I have all the 6 speakers for 5.1 and the surround monitor controller by SPL. Some headphones for people if they need them (AKG) and the 16 channel of ASP880 microphone pre-amps. Rated very highly and working well with the UAD system for giving clear, non-coloured sound.
Thurs April 22nd
Guys showed up at the normal time and did the bits they needed to for the right corner. Concrete was delayed until 14 (they did not actually come til 15) so they worked more on the walls and window sills. Starting to go up at an angle now. Anyway, sadly, they only got the first 6m3 of cement poured and it looked like the wall was starting to bulge or bend out tiny bit in the middle so Paul made the call to not pour the rest. The risk was too high. We may end up having to pay for the 6m3 of concrete in the 2nd truck if they could not find another job to use it on. Damn.. Anyway, the last cement in the tube they used next to the wall where they will put some of the old ruin stones. Progress but a bit of a set back as on Monday, they will have to take down the front wall panels and supports and start over completely to do it again, so this is a bit of a set back, perhaps 3-4 days of work. Not sure..
Friday April 23rd
Paul called the night before and said they had a change of plan and in order not too loose too many days, they would shore up the wall this morning and gently pour the rest of the cement 6m3 by hand. So they showed up at normal time and sure enough, worked their asses off and poured like 60 mixers of cement to get to the top of thee 3.5m wall. They worked super hard in the afternoon with no break between like 14-18.. We had a beer together afterwards. Wow.. Now they will let the wall set for 3 days and be back on Tuesday to remove the frames and see what the wall looks like. Paul says if the bulge is too much in the middle, they will have to shave some of the concrete back in order to make the wall straight enough. We just have to wait and see. I am very glad they did this as now, they will likely be able to finish all the walls next week and put the plasterboard into the building and start on the roof the week after.
April 27th
Guys showed up at 8:45 like normal. It was nice in the morning but it looked threatening rain all day with masses of black clouds around but in the end it hardly rained. Gil and José managed to get about half the panels off yesterday. It is a big job to disassemble the supports and all the screws, supports, ties, etc.. then you have to clean all the cement off the everything as well. It is quite clear now that the wall is far from straight. Not sure how they will deal with this but it for sure bends out quite a bit. Also appears to lean. We will see, when it is fully exposed tomorrow.
April 28th
Had a nice chat with Paul yesterday about his thoughts on the timing of some things with the building. I am trying to get Joules and Joe, in the loop of when we will need them to come and do the wiring in the walls. Paul figures next week they will finish all the walls and put in the vega for the roof. He will order up the plasterboard and put it inside the building before they do the roof. He figures they will have the roof and basic framed walls inside up by first week in June, if the weather is not interfering. So then Joules and Joe can come up and do the wiring in the open framed walls and then they can put the other 2 layers of plasterboard up.
April 29th
The guys did not show up until after lunch today and it was only Gil. Had an emergency pool repair. He managed to get all the framing off the back of the wall so I assume they will finish it and start to do the rest of the brick work on Friday.
April 30th
José has a bad shoulder so is slowed down quite a bit but they managed with Paul’s help to get all the metal shuttering off and the concrete cleaned off (big job). They swept and cleaned up the inside of the building and now are ready to finish the walls. Paul figures 3-4 days and all the walls will be done. He will look into the plasterboard on Monday while the guys do the walls. They lowered down some bricks so that they are ready to go.
I spoke to Joe about walls today as Joules and Joules is suggesting is to just attach the metal framed wall filled with rock wool to the brick wall. Then doing the wiring and put up the two layers of plasterboard. The inner layer will be the blue-green weather resistant type and the outer, normal plasterboard. I know this will not decouple the the live and entrance room from the building but Joules is planning to float and completely isolate the control room from the rest of the building. He says since I am on a budget and we have massive walls and the building is surrounded by granite on three sides, and your nearest neighbour is 300m away up the road behind the building, we don't need more isolation of sound. I have asked Stuart what he thinks, if this will compromise things too much, rather than do proper MSM or MAM walls as was originally planned. I will have a bit more floor space and it will be much easier for Paul (less labour) and cheaper for me.
May 3rd
We will have amazing weather all week so they should easily be able to get the bricks done this week. Doubt they can get the roof as well since it will rain for 3 days in the following week. We only have the crane until May 16th, I think.
May 4th
Paul was here for a few hours helping them yesterday and they managed to finish most of the side walls to about 3m and then add 2 layers of blocks on the huge concrete wall, which has to be blocked up to about 6m. They added some blue insulation to the outside of the building on the ruin side by the pool. There is not a lot of space in there. I am still not sure how they concrete and water seal that?? Anyway, he said they would trim the top of the ruin wall to match the height of the building roof and put tiles over the top of the ruin. This is great, then we don’t have to worry about water getting in on that side at all.
May 5th
They arrived about 11 today and started to continue on the back wall blocks. They have about 6 layers to go, I guess. I doubt they will finish all the walls today but for sure tomorrow. Paul got one quote for the plasterboard today. 6€ for the weatherproof and 4.8€ for the normal plasterboard. He estimates it is 110 boards and will take 10,000 screws!! He thinks he can get a better price at another place. They hope to get it delivered soon so then they can start on the roof.
Image not preserved: D4F143CC-14FF-44C4-89E0-1F211D304F5C_1_105_c.jpeg
Image not preserved: A9CA8719-907E-45CD-B87F-D12143B828FC_1_105_c.jpeg
Image not preserved: 7B4D1489-6A9E-45AE-AF05-7F53048BC309_1_105_c.jpeg