Time for another update, or, how I spent my Spring...
Not very dramatic but this is a pic after finally cutting the lighting circuit in the room. I ran extension cords to all the lights in the room and wired up a temporary box in the corner on another circuit. Later this year I'll be removing those receptacles, patching the holes and adding another layer of drywall to this ceiling (which is the outer leaf).
For the most part, it's been about the beefing up -- a very slow process. This one of the removed windows, after being framed in with new siding and caulking underway. The window and doors take so much longer due to the extra pieces of drywall needing to go in smaller spaces.
Here's an example of an area above one of the removed windows. This is after removing the drywall & insulation, then cleaning up the space and caulking the framing. Here you can see the new piece of siding butting up to the old one. I also recently discovered it helps to write the dimensions in each space so I don't have to keep re-measuring. I just measure exactly & then remove 1/4" from each edge.
Now with the drywall and some backer rod.
Caulked in place with the cleats. There is still a spacer on the bottom. I typically come back the next day to fill those in.
Here's an entire wall in various states of progress. I added strapping to hold up the insulation. Not sure if I mentioned this but all the paper has been removed since I will have a proper vapor barrier on the inner leaf.
At this point I'm about 60% done with the wall beefup...
More to come...