dealing with floor/wall gap and cable penetration
Posted: Sun Jan 15, 2017 1:02 am
Hello All,
Back again with questions I shouldn't be needing to ask!
Am at a stage of my construction where I am facing some imminent decisions that by rights I should have addressed ealier in my planning stage but I am where I am and for that am feeling pretty self-condemning!
following on from recent posts I need advice on a couple of key issues.
Floor will soon go down, currently there is a concrete slab with DPM ontop. next will go 50mm Celotex then underlay and laminate flooring ontop.
befor getting to next stage I have discussed wth builder (not studio build specialist) about addressing the 25mm gap between the concrete base and the walls (2x15mm PB). He seems to think this gap doesn't need caulking but to me alarm bells are ringing loud!
According to my research on this and other forums it needs backer rods pushed into all gaps then caulked thoroughly to fill the gap fully, some gaps may not fit backer rods so just fill with caulk in these cases?
Am I correct?
I assume acoustic caulk is best but any other suitable alternative suggestions welcome.
Other issue ringing 120db alarm bells is the penetration of the electrical armoured cable which will bring power to the structure.
The original feeding in of the cable has not been done correctly as far as I can see. cable was brought in via external trench then into the cavity (now filled with 100mm Rockwool) between the external OSB layer. It was brough in before the PB layers were put up and not line of sight penetration (came from below then up to penetrate PB at higher level) but was not put in a conduit so therefore no decoupling of conduit sections.
pic shows a massive hole with cable penetration showing, also visible through the hole under the plasterboard is the top of a resilient channel. Have included pics and a simple sketch (PB fixed to studs but these not shown in sketch)
Discussing with electrician how to seal this to the best degree possible prior to installing service panel at that location I outlined that the cable should be threaded into a conduit going down as far as possible then conduit stuffed with rockwool (down into conduit as far as possible) then sealed with caulk as far into conduit mouth as possible and where it appears at interior surface. He says he can't do that!
I am aware that this is a solution far from ideal but is it the best possible remedy to what I see as an appalling situation?
Also notice that inside the hole the 2 flanges of the visible RC have plasterboard dust/powder in between which will have to be got out to avoid short-circuiting the isolation provided by the RC.
A also assuming the empty space now visible behin dthe PB needs to stuffed full of RW?
Any advice would be very valued
thank you
Jose
Back again with questions I shouldn't be needing to ask!
Am at a stage of my construction where I am facing some imminent decisions that by rights I should have addressed ealier in my planning stage but I am where I am and for that am feeling pretty self-condemning!
following on from recent posts I need advice on a couple of key issues.
Floor will soon go down, currently there is a concrete slab with DPM ontop. next will go 50mm Celotex then underlay and laminate flooring ontop.
befor getting to next stage I have discussed wth builder (not studio build specialist) about addressing the 25mm gap between the concrete base and the walls (2x15mm PB). He seems to think this gap doesn't need caulking but to me alarm bells are ringing loud!
According to my research on this and other forums it needs backer rods pushed into all gaps then caulked thoroughly to fill the gap fully, some gaps may not fit backer rods so just fill with caulk in these cases?
Am I correct?
I assume acoustic caulk is best but any other suitable alternative suggestions welcome.
Other issue ringing 120db alarm bells is the penetration of the electrical armoured cable which will bring power to the structure.
The original feeding in of the cable has not been done correctly as far as I can see. cable was brought in via external trench then into the cavity (now filled with 100mm Rockwool) between the external OSB layer. It was brough in before the PB layers were put up and not line of sight penetration (came from below then up to penetrate PB at higher level) but was not put in a conduit so therefore no decoupling of conduit sections.
pic shows a massive hole with cable penetration showing, also visible through the hole under the plasterboard is the top of a resilient channel. Have included pics and a simple sketch (PB fixed to studs but these not shown in sketch)
Discussing with electrician how to seal this to the best degree possible prior to installing service panel at that location I outlined that the cable should be threaded into a conduit going down as far as possible then conduit stuffed with rockwool (down into conduit as far as possible) then sealed with caulk as far into conduit mouth as possible and where it appears at interior surface. He says he can't do that!
I am aware that this is a solution far from ideal but is it the best possible remedy to what I see as an appalling situation?
Also notice that inside the hole the 2 flanges of the visible RC have plasterboard dust/powder in between which will have to be got out to avoid short-circuiting the isolation provided by the RC.
A also assuming the empty space now visible behin dthe PB needs to stuffed full of RW?
Any advice would be very valued
thank you
Jose